Iteration 11

The goal of this iteration is to complete the conversion of the extensions over to the version 6.0 core, and to get the GDAL proof-of-concept for the LSML working on Windows.

  • Phase: Transition
  • Dates: December 10th - 20th, 2010

Tasks

  • Extensions
    • Sri will incorporate LSML into the Core and two extensions: age-only succession and base fire. He will run system tests to ensure that age-only + base fire works.
    • Rob and Sri will update all other extensions to work with LSML.

Assessment

  • To Be Completed December 20, 2010